Report from the University Landscape Trenches : Financial shoring collapsing, trouble brewing

Received from Rhodes
Mon, 24 Oct 2016 at 9:14 p.m.

Saturday’s ODT had an interesting article about delays on the troubled University of Otago landscaping project. This article is the canary in the University construction goldmine, as there are other even much larger disputes brewing on current University projects that certainly will become a goldmine for the contractors, to the detriment of the University’s financial health.

uoo-landscaping-20160508_135933Hoarding, University of Otago

Mr Mackay said the complications on the landscaping included “replacing old water, sewage and drainage pipes”. What he did not say is that this work was meant to have been done two summers ago, BEFORE the academic year, but due to the project management, it was not. However, this landscaping project is small beer, there are much bigger problems looming.

The University, in their biggest ever project, at the 11th hour, on the “advice” of a contractor, Fletcher Construction, who we understand did not even finally submit a bid, told the University they could save a few hundred thousand on the $100 million project by deleting the need for a cost control schedule…. that would have severely limited what the contractors could charge for changes and extra work. In a monumental display of incompetence, the University stopped production of the schedule – which was already underway and had to be part paid for anyway and put the drawings and specifications out to tender without a schedule. If the drawings were 100% complete and the University wasn’t to change its mind that would be OK, but the Pope is more likely to preach at Canterbury Cathedral than this happening. Of course, the drawings are woefully incomplete, and the arguments and changes have started. Watch out for Someone from the University Property Services division, in about a year, to be in full dissembling mode about the delays, and how, “even though it’s six months late, it’s still on budget”. If that is the case, the budget has massive doses of incompetency cover built into it !

An additional problem that’s about to come home to roost in the University and Otago Polytechnic’s coffers is insistence, by University Property Services, on the use of “Early Contractor Involvement” (ECI). (Someone at University Property Services has never met a new construction euphemism he did not use or a project delay that he could not justify). Both the University and Polytech on recent large projects have engaged in tender processes where there is no fixed sum, because the documents are far from complete, and the current fashion du jour is to have “early contractor involvement” where the builders are paid to be involved in the design phase, to provide “constructability” expertise. Basically the builders make a submission to say what nice people they are, and advise percentage site overhead and profit margins they would build the project for. The rest of the cost, about 85-90%, is just guesswork. (“Provisional Sums”). This process allows the “tender evaluation team” (mainly the Architect and the University) to choose who they want, without regard to price, because the weighting for “non-price attributes” is a lot more than 50% of the total weighting.

On both the University commerce building project, just started by Naylor Love, and the Polytechnic Hostel project (also won by Naylor Love), this was the process. Both projects are around $20 million all up. Significantly, the architect on both projects was Mason & Wales. There were a number of other consultants in the design teams. The politest way to put the next point is that there appeared to be “confusion” about the proposed early contractor involvement process from the team. It was thought, inexplicably, that this wonderful new system of selecting builders without worrying about price meant not only did they get to choose ones with very high margins who wouldn’t cause problems when the inevitable design problems arose, some consultants also thought that they could charge full fees and offload all of the detailing onto the builder…. which of course did not happen. Builders, in the South Island anyway, do not employ armies of CAD operators who can document bespoke large projects. That is what designers are for…. In both cases, the successful Naylor Love bid was hundreds of thousands of dollars more expensive than lower bids. Also in the case of both bids, the University and the Polytech paid a premium of around $500-600,000 to have the “ECI/ constructability” experience of Naylor Love…. only to find that the advice received was NOT what was expected…. the Polytech project has been now costed by Naylor Love and is $1.5-2.0 million over budget, and the “expert” constructability / ECI advice that the Polytech effectively paid $600,000 for is…. wait for it…. to make the building smaller. Hmmm, expensive and brief advice! Best not tell the Humanities students ! The other unsuccessful contractors may well feel aggrieved about how this process played out, as before they were even allowed to provide a proposal they had to prove their capability and experience to do the work, so in theory all tenderers were equally capable, and there was no logical reason for the favouritism to Naylor Love…. but were there other reasons ? There appears no meaningful financial oversight, the project teams seem a law unto themselves, and the suspicion is that both institutions’ funds are being spent in a very free and easy fashion.

[ends]

Related Posts and Comments:
18.7.16 Misero-mercenary at U of O
1.7.16 No one wants to work for U of O
25.9.15 University calling Property Services
28.3.15 University of Otago landscaping
24.7.13 University: Leith flood protection scheme and landscaping
31.5.13 University of Otago development plans
27.5.13 Carisbrook and Leith flood protection
17.11.10 Leith Lindsay Flood Protection Scheme
17.5.10 Campus Master Plan
28.1.10 University of Otago Campus Master Plan

Posted by Elizabeth Kerr

This post is offered in the public interest.

6 Comments

Filed under Architecture, Business, Construction, Design, Dunedin, Economics, Finance, Media, New Zealand, Otago Polytechnic, People, Pet projects, Politics, Project management, Property, Public interest, Resource management, Site, Travesty, University of Otago

Tertiary larks squeeze DCC ratepayers for $30,000

“The two [Auckland] firms had been hired to prepare concept plans and options for projects to improve the pedestrian and cycling environment in and around the tertiary campuses. […] This will enable projects to be ‘picked off’ by the various institutions together or individually.” –Susan Lilley, DCC (via ODT)

● Why are DCC, university and polytechnic not buying LOCAL?
● (Student Ghetto) The streets are PUBLIC, aren’t they? Or are they.
● University and polytechnic not paying enough rates?!
● Heaps of other questions?!

Kate Wilson said Chow Hill Architects and Flow Transportation were hired to come up with a plan, at a cost of $88,000, with the city council paying $30,000, and the rest split between Otago Polytechnic and the University of Otago. (ODT)

Cr Kate### ODT Online Thu, 7 Aug 2014
Auckland firms work on tertiary streetscape
By Vaughan Elder
Two Auckland firms have been hired to investigate options for a revamp of Dunedin’s tertiary precinct, which could include making some areas pedestrian only. The work on the streetscape in the tertiary precinct is being overseen by the “tertiary precinct planning group”, which includes representatives from the Dunedin City Council, Otago Polytechnic, University of Otago, Otago Regional Council, Otago Museum and Southern District Health Board.
Read more

Related Posts and Comments:
5.8.14 DCC staff-led CBD projects that impact ratepayers…
4.8.14 Cr Wilson’s integrity ‘in tatters’
1.8.14 DCC: Sorting THE MESS
28.7.14 DCC: Residents’ Opinion Survey 2014
5.7.14 DCC’s debt level — who do you believe?
23.6.14 DCC Annual Plan 2014/15 + Rugby and Rates
2.6.14 DCC: Slip in service levels, why?!
22.5.14 DCC Transportation Planning —ANOTHER consultation disaster

1.8.14 University Partyville, North Dunedin: Put the cameras in ~!!
16.7.14 Stadium: Out of the mouths of uni babes…. #DVML
22.3.14 Dunedin North care less filthy slum
19.3.14 Dunedin North drunks
15.2.14 University of Otago: Starter questions for Harlene
10.2.14 University of Otago major sponsor for Highlanders
19.8.13 Cull on senility (firing up graduates)
31.5.13 University of Otago development plans
25.3.13 University of Otago: NEGATIVE PRESS: Weekly disorder…
20.2.12 University of Otago student orientation
17.12.11 Stadium + Cull love = University of Otago + OUSA party
23.11.11 Judge Oke Blaikie finally said it
20.5.10 Hahaha if you’re still thinking Campus Master Plans look…
17.5.10 Campus Master Plan

North Dunedin - Where Campus Watch are operating [otago.ac.nz] 1North Dunedin – Where Campus Watch are operating [otago.ac.nz]

Posted by Elizabeth Kerr

*Image: Cr Kate by whatifdunedin

Leave a comment

Filed under Architecture, Business, Construction, Cycle network, DCC, Democracy, Design, Economics, Geography, Heritage, Hot air, Media, Museums, Name, New Zealand, NZTA, ORC, Otago Polytechnic, People, Pics, Politics, Project management, Property, SDHB, Site, Tourism, Town planning, University of Otago, Urban design, What stadium

University of Otago development plans

University of Otago Registry and Clocktower Building [physics.otago.ac.nz] 1University of Otago Stadium building [otago.ac.nz] 2When previously . . .

### ODT Online Thu, 30 May 2013
$358m vote of confidence
By Vaughan Elder
The figure the university has earmarked for construction, from last year until 2020, was revealed in the university’s priority development plan, obtained by the Otago Daily Times under the Official Information Act. The plan includes 22 projects, 20 of which are in Dunedin. The university declined to reveal the budgets for individual projects, citing commercial sensitivity, but put the total budget for the work at $357.8 million.

University chief operating officer John Patrick said the projects were included in the plan for a number of reasons, including to accommodate growth, to improve building layout and efficiency and health and safety.

Asked how the university could afford such a large amount of work, given what it had previously described as a “difficult” funding environment, Mr Patrick said: “The University of Otago has a fiscal strategy that is designed to provide funding for capital development.”
Read more

30.5.13 ODT: University updates staff on quake work

Posted by Elizabeth Kerr

*Images: (top) physics.otago.ac.nz – University of Otago Registry and Clocktower; otago.ac.nz – Building at University Plaza

85 Comments

Filed under #eqnz, Architecture, Business, Construction, Design, Economics, Heritage, Innovation, Inspiration, Media, Name, People, Politics, Project management, Property, Site, Urban design

University Plaza at the stadium

### ODT Online Sat, 15 May 2010
Plaza plans a mystery
By Chris Morris
Just what will the Forsyth Barr Stadium’s plaza look like? That is a question the University of Otago is not ready to answer. The Otago Daily Times contacted university property services director Barry MacKay this week, seeking an update on planning for the stadium plaza’s final design.
Read more

****

What is purposeful dialogue? I’m not sure if the university’s communications staff are communicating anything usefully, lately.

Don’t ask about the fiasco over the pending public exhibition of the tertiary precinct development plan (aka ‘master plan’) – since when do communications staff know what exhibition curation and COMMUNICATION mean.

Furthermore, since when would a public communciations exercise ‘last for just one night’? Best ask communications staff how they arrived at that idea, for starters.

Did communications staff actually ask for a full explanation of the project brief and understand the work the exhibition has to do for public consultation before bulldozing changes.

Why are they MANDATING which authors/contributors and sponsor/supporters of the exhibition cannot have their logos displayed with the exhibition materials. Rhetorical.

Back to friggin’ business school for the lot of them at ‘communications’.

Post by Elizabeth Kerr

Leave a comment

Filed under Architecture, Construction, Design, Economics, Events, Geography, People, Politics, Project management, Site, Sport, Stadiums, Urban design

What is the New Zealand Urban Design Protocol?

The New Zealand Urban Design Protocol is a voluntary commitment to specific urban design initiatives by signatory organisations, which include central and local government, the property sector, design professionals, professional institutes and other groups.

The Protocol aims to make our towns and cities more successful by using quality urban design to help them become:

* Competitive places that thrive economically and facilitate creativity and innovation
* Liveable places that provide a choice of housing, work and lifestyle options
* A healthy environment that sustains people and nature
* Inclusive places that offer opportunities for all citizens
* Distinctive places that have a strong identity and sense of place
* Well-governed places that have a shared vision and sense of direction

The Protocol identifies seven essential design qualities:

* Context: Seeing that buildings, places and spaces are part of the whole town or city
* Character: Reflecting and enhancing the distinctive character, heritage and identity of our urban environment
* Choice: Ensuring diversity and choice for people
* Connections: Enhancing how different networks link together for people
* Creativity: Encouraging innovative and imaginative solutions
* Custodianship: Ensuring design is environmentally sustainable, safe and healthy
* Collaboration: Communicating and sharing knowledge across sectors, professions and with communities.

Learn more about the Protocol here.

Local signatories to the Protocol include:

Dunedin City Council
University of Otago

Leave a comment

Filed under Economics, Events, Hot air, Politics, Project management, Town planning