Tag Archives: Dunedin Town Hall Redevelopment Project

DCC LGOIMA Response : Wall Street Mall and Town Hall Complex

Email correspondence.

From: DCC Governance Support
Sent: Friday, 20 January 2017 8:48 a.m.
To: Elizabeth Kerr
Subject: Official information response 280070 Council Buildings WOF

Dear Ms Kerr,

Official information request for information about COUNCIL BUILDINGS WOF

I refer to your official information request dated 28-November-2016 for the following information. Our response to each question is in red font [italics at this website -Eds]:

1. Does the council-owned Wall Street Mall (211 George St, Dunedin) have a current building warrant of fitness, and if not why not?

The Wall Street Mall at 211 George Street does not have a building warrant of fitness. The current status of the Wall Street Mall building warrant of fitness is that a Letter in Lieu was issued for the Specified Systems 15.3, 15.4, 15.5 because a full 12 months’ worth of daily inspections had not been completed. We can confirm that since July, 2015, these daily checks have been in place and this will not be an issue for subsequent warrants of fitness.

Please note that where a Letter in Lieu is issued this means the Independent Qualified Person (IQP) confirms that the systems in the building are working as they should and are compliant.

2. Since the construction of Wall Street Mall was completed in what years has it had a current building warrant of fitness issued, and if not why not?

Mar 2012 – Outstanding form 12A for Specified System 6 (Riser Mains).
Mar 2013 – Letter in lieu issued for Specified System 6 (Riser Mains).
Nov 2013 – Building Warrant of Fitness Received.
Sep 2015 – Letter in lieu issued for 2014/15 & 2015/16 compliance year for Specified System 15/3.
Regarding the reasons for this, please refer to the comments of the Manager, City Property below.

3. Does the council-owned Dunedin Town Hall complex, including Glenroy Theatre, Metro Cinema, and Municipal Chambers, have a current building warrant of fitness(s), and if not why not?
Since the major Dunedin Town Hall Redevelopment Project was completed (including Glenroy Theatre, Metro Cinema, and Municipal Chambers) in what years has it had a current building warrant of fitness(s) issued, and if not why not?.

There is no building warrant of fitness in place for these premises. Instead the Dunedin Town Hall complex, including the Municipal Chambers, Dunedin Centre and the Metro Theatre, have a Certificate of Public Use in place. This means the buildings are safe to use.

These buildings do not have a current Building Warrant of Fitness as, at time of writing, no current Code of Compliance has been issued following the completion of the redevelopment work as there were some building elements requiring attention relating to fire engineering. These elements have been completed and the documentation submitted to DCC Building Compliance for Final Inspection and issue of the Code Compliance. Once the Code Compliance Certificate has been issued there will be nothing to prevent the issue of a warrant of fitness at the next inspection.

If you wish to discuss this information with us, please feel free to contact Property Manager Kevin Taylor on 03 477 4000. Mr Taylor has prepared the following report for the chief executive. This is provided for your information:

The DCC Property department has previously engaged an outside contractor to administer and manage the BWOF compliance on DCC properties, in particular the Wall St Mall. In early 2015, the Building Compliance aspect was sold to Logic Project Management Consultants and a new company called Logic FM was formed and took over the majority DCC BWOF administration.

Our experience as we undertake building audits is that previous advice may have been too lax or liberal in assessing the building’s compliance with particular codes, specifically around fire protection and fire cells. We have also found that the inspections that were contracted to have been undertaken were not fulfilled, leaving gaps in the compliance processes. Thus the BWOF could not be issued by deadline or due dates.

Subsequently, it has been our experience that Logic FM has been interpreting code compliance components beyond that required by the law and schedules to the Acts governing the specified systems. Thus we have experienced a number of “notice to fix” instructions issued which are in error.

To satisfy ourselves that the BWOF is being managed and administered as it should be, DCC Property has engaged independent experts, especially structural and fire engineers, to review the building’s specified systems and as-built safety components. These independent audits have been completed and the required reports and Letters in Lieu issued to enable the DCC Building Authority to issue the BWOF.

The BWOF owners inspections have been brought in-house and are undertaken by the property team’s asset management staff. IQP inspections continue with the specific trades as required.

Yours sincerely

Governance Support Officer
Dunedin City Council Continue reading

19 Comments

Filed under Architecture, Business, Construction, DCC, Democracy, Design, Dunedin, DVML, Economics, Education, Finance, Fire and Emergency NZ, Heritage, Infrastructure, New Zealand, OAG, Ombudsman, People, Politics, Project management, Property, Public interest, Resource management, Site, Structural engineering, What stadium

ODT: Vandervis v Cull

Dave Cull merge v1

‘Mr Cull maintained he was correct to call Cr Vandervis a liar during a furious bust-up at a council meeting last December, telling the Otago Daily Times yesterday “a lie is a lie”.’

### ODT Online Sat, 7 May 2016
Threat to ‘double damages’
By Vaughan Elder
Councillor Lee Vandervis has threatened to “double the damages” from defamation action after Dunedin Mayor Dave Cull stood by calling him a liar. […] Cr Vandervis launched the defamation action this week, saying Mr Cull calling him a liar during a discussion on a new council procurement policy was incorrect and defamed him. A letter sent to Mr Cull by Cr Vandervis’ legal counsel, Alistair Paterson, said he would be willing to forgo defamation action if Mr Cull paid his legal costs and made a public apology in a full council meeting filmed by Dunedin Television and in the presence of Allied Press [Otago Daily Times] reporters.
Read more

Channel 39 Published on Dec [14]*, 2015
Councillor asked to leave meeting
Councillor Lee Vandervis was instructed by Mayor Dave Cull to leave a Dunedin City Council meeting today. The request came after Cr Vandervis alleged that tender contracts could not be secured unless a relationship was developed with staff. The Mayor rejected his claims, saying he had no proof. Cr Vandervis then proceeded to continue discussing the matter and was asked to leave.
Note: Incorrect date of meeting given at YouTube entry.

Dunedin City Council Published on Dec 15, 2015
[full meeting video – relevant segment near end from 2:07:19]

Unconfirmed Minutes of Meeting (14.12.15)
No reason given for minutes as yet unconfirmed by Council.

Related Posts and Commments:
14.3.16 Cr Vandervis co-operates with investigators #mediaslant
20.12.15 More emails —DCC aftermath of full council meeting 14.12.15
19.12.15 Member of the public lays Conduct complaint against Mayor Cull
15.12.15 Santa Cull’s idea of standing orders 14.12.15 #xmasface

█ For more, enter the term *vandervis* in the search box at right.

Posted by Elizabeth Kerr

Election Year —this post is offered in the public interest.

*Image: dunedintv.co.nz – archivemash by whatifdunedin

67 Comments

Filed under Business, DCC, Democracy, Dunedin, Economics, Events, Finance, Media, Name, New Zealand, Ombudsman, People, Politics, Project management, Property, Public interest, Site, Travesty

More emails —DCC aftermath of full council meeting 14.12.15

Updated post
Mon, 21 Dec 2015 at 1:00 p.m.

“I have told you personally of a relationship with a DCC manager where I had to pay a 10% backhander to get a contract.” –Cr Vandervis to Mayor Cull

### ODT Online Mon, 21 Dec 2015
Contract fraud call at DCC
By Chris Morris
Dunedin city councillor Lee Vandervis’ actions will form part of a fresh fraud investigation inside the Dunedin City Council, after he claimed to have paid a backhander to secure a council contract. Council staff have confirmed his actions would be examined by the council’s internal auditors, Crowe Horwath, under the council’s new fraud prevention policy.
Read more

Otago Daily Times Published on Dec 14, 2015
Cr Lee Vandervis instructed by Mayor Dave Cull to leave meeting.
[Vandervis statement around 1.25 mark]

Received from Lee Vandervis
Sat, 19 Dec 2015 at 10:56 p.m.

Re: Town Hall Redevelopment Project and Citifleet fraud allegations

—— Forwarded Message
From: Sandy Graham
Date: Fri, 18 Dec 2015 02:37:27 +0000
To: “Council 2013-2016 (Elected Members)”
Cc: “Executive Leadership Team (ELT)”
Subject: Additional LGOIMA emails re Various matters related to allegations from Monday meeting

Councillors

Please find attached an additional PDF that was included in the information provided to the ODT but got missed in my earlier email to you.

Apologies.

Sandy

From: prncc209@dcc.govt.nz
Sent: Friday, 18 December 2015 12:48 p.m.
To: Sandy Graham
Subject: Message from KM_C454e

(1) Attachment:
SC454E0591715121812470 [683890] (PDF, 169 KB)
Lee Vandervis to Bidrose 28.6.15 [thread]

Related Post and Comments:
19.12.15 DCC aftermath of full council meeting 14.12.15 (emails released)

Posted by Elizabeth Kerr

29 Comments

Filed under Architecture, Business, Citifleet, Construction, DCC, Democracy, Dunedin, Economics, Infrastructure, Name, New Zealand, OAG, Ombudsman, People, Police, Politics, Project management, Property, SFO

DCC dirty laundry/fleet cars #LGOIMA

What if Dunedin online

Related Posts and Comments:
18.9.15 DCC suddenly wakes up! *cough —after fleet car pointers from years back
● 16.9.15 DCC: Know your council ‘chair-leaders’ #pillowtalk [THE EMAILS]
4.8.15 Hundreds of DCC Staff receive fraud detection/prevention training #OMG
21.7.15 DCC: LGOIMA requests for the last month
24.4.15 DCC re Dr Bidrose’s time as most senior Citifleet Manager

Belatedly….
19.9.15 ODT: Information requests irk councillors

The latest salvo came after Cr Lee Vandervis made public an email exchange with Crs Benson-Pope and Richard Thomson, copied to other councillors and staff, earlier this week.

Cr Vandervis did not respond to ODT requests for comment yesterday.

In his emails, published online, he blamed a lack of information coming from council staff for the “tedious” need to resort to Information Act requests.

Biblical proportion…. [thanks RMN]

Matthew 23:23-25
23 “Woe to you, scribes and Pharisees, hypocrites! For you tithe mint and dill and cummin, and have neglected the weightier provisions of the law: justice and mercy and faithfulness; but these are the things you should have done without neglecting the others. 24 “You blind guides, who strain out a gnat and swallow a camel! 25 “Woe to you, scribes and Pharisees, hypocrites! For you clean the outside of the cup and of the dish, but inside they are full of robbery and self-indulgence….

Posted by Elizabeth Kerr (online)

5 Comments

Filed under Business, Citifleet, DCC, DIA, Economics, Enterprise Dunedin, Hot air, Media, Name, New Zealand, OAG, Ombudsman, People, Police, Politics, Project management, Property, SFO, Transportation, What stadium

DCC: Know your council ‘chair-leaders’ #pillowtalk

It’s with some fascination if not repulsion that Whatiffers can observe bullying by standing committee chairmen continuing unabated on the mayor’s watch.

Cr Thomson’s historical on camera stunts of addressing or referring to Cr Vandervis as “my good friend” are, how shall I say, unchaste and deceptive in the context of what follows below.

Cat Whisperer by Goodwyn [www.toonpool.com] tweaked 1

Two emails received tonight.

Received from Lee Vandervis
Wed, 16 Sep 2015 at 9:26 p.m.

█ Message: Differing Councillor views that may be of interest.
Cheers, Lee

—— Forwarded Message
From: Lee Vandervis
Date: Tue, 15 Sep 2015 22:41:19 +1200
To: Richard Thomson, Grace Ockwell, Sue Bidrose, Sandy Graham
Cc: Dave Cull, Kate Wilson, Chris Staynes, Jinty MacTavish, David Benson-Pope, Hilary Calvert, Aaron Hawkins, Mike Lord, Andrew Whiley, John Bezett, Doug Hall, Neville Peat, Andrew Noone, Ruth Stokes
Conversation: OIA Request
Subject: Re: OIA Request

Actually Richard, the Lamborghini has become symbolic of many other very visible excesses, but let us stick to Council issues.

For many years I used to make all the information I had available in very candid discussions with staff, who often then failed to investigate appropriately. Citifleet is a prime example, and this and other examples has taught me that a publicly funded organisation is poorly motivated to investigate itself.
Without my LGOIMA requests the incredibly belated Citifleet ‘investigation’ might never have happened, as it did not happen for over a decade before. Have you counted the cost of that multimillion dollar fraud as a percentage of the cost of processing my LGOIMA requests?
Do you not realise that most of my LGOIMA request arise from questions and allegations from members of the public that I represent?

Even when an internal investigation does prove that for instance over quarter of a million of public funds was paid to a contractor to clear mudtanks and none were cleared, nothing appropriate seems to happen at the DCC without publicity. Hence my now having to get the public involved when things are not sorted internally.
When you claim that needing information “of how the information relates to possible wrong doing” is necessary to get information, this is absurd. It is much easier to simply search ‘Stihl chainsaws’ and forward what DCC files information appears. Similarly a vehicle registration number. Just search the registration number and forward the files – easy, quick, no thinking required, little time wasted considering whether ‘particular staff have been involved in possible wrong doing’ etc.

Why is it that our staff can have all this information, but not want to share it with us the supposed decision makers when we request it?
Answer – information is power – and bureaucracies generally do not want to share it, especially with supposed decision makers.

Don’t you dare suggest that I do not give a toss, as you have no way of knowing the state of my mind or the work that I do, and don’t you dare suggest that my approach has failed to identify fraudulent behaviour, as you similarly do not know what has gone into, for instance, Citifleet, Jacks Point/Luggate, mudtanks, Noble, Town Hall redevelopment, or the almost complete turnover of senior managers at the DCC in the last few years.

I will continue to carry on in the manner I believe to be appropriate, and I do not seek any advice on my manner from of you.

Regards,
Cr. Vandervis

———————————

On 15/09/15 9:48 pm, “Richard Thomson” wrote:

Actually Lee my concern is quite the opposite. If there is fraud taking place I want to see it caught. That is why in the Otago DHB when someone came to me with an anonymous tip off and no evidence to back it I initiated a full investigation within half an hour. And I know what some of the consequences are of taking action. They include having to have endless questioning of your integrity/intelligence/ etc by people such as yourself and your fellow travellers on the likes of What If. You have no idea how terribly amusing it is to regularly be accused, because you did the right thing, of “failing to notice the Lamborghini in the carpark”. Never mind that I never had a carpark so didn’t go in the carpark building, or that the fabled Lamborgini was only owned for a few days. Or indeed, had I gone in the carpark building for a random look around and spotted a Lamborghini I would probably have assumed it belonged to a surgeon anyway. So bearing that personal history in mind here is what really pisses me off.

When you make accusations but when virtually begged to make the information available to the CEO so it can be investigated you respond that the “only way you will be making the information available will be through the pages of the ODT”. As you did at the Audit Committee meeting.

When you put in OIA requests and refuse to give any indication of how the information relates to possible wrong doing. Lets think chain saws here. So in the end the only way the OIA can be responded to is to make general inquiries all over the place thereby pretty much ensuring that if there has been dishonesty the person involved will have plenty of time to bury any evidence.

When you seek “all documentation” about a motor vehicle without giving a toss whether the inquiries around that might harm any investigation if there has been wrong doing because the people responding to the request will have no idea if they are going to tip off unknowingly a suspect.

It ought to be of some concern to you by now that your methods and approach have failed to catch any fraudulent behaviour but that the methods of Mr McKenzie that you so disparage have caught a number. Perhaps the fact that people do come to you with info might actually result in people being caught if you worked with people instead of carrying on in the manner you do.

R

[contacts deleted]

———————————

From: Lee Vandervis
To: Richard Thomson; Grace Ockwell; Sue Bidrose; Sandy Graham
Cc: Dave Cull; Kate Wilson; Chris Staynes; Jinty MacTavish; David Benson-Pope; Hilary Calvert; Aaron Hawkins; Mike Lord; Andrew Whiley; John Bezett; Doug Hall; Neville Peat; Andrew Noone
Sent: Tuesday, 15 September 2015 8:59 PM
Subject: Re: OIA Request

Re: OIA Request

I note Richard, that you and some others are quite happy to get on with running a city without knowing who is stealing what or how much things cost to run the city.
My regular voting against Council spending motions often arises because there is simply not enough information made available to justify voting for.
If staff reports provided adequate relevant information, and if rate-paid reports like the $300,000 Deloitte investigation information were made available to us who need to make related decisions, none of this tedious LGOIMA process would be necessary. It is a shame that I have to go to so much effort just get basic information, and that so few others can be bothered.

Cr. Vandervis

———————————

On 15/09/15 5:27 pm, “Richard Thomson” wrote:

Hi,

Could I please file an official information act request asking what the cost to Council has been of answering Cr Vandervis’s official information act requests over the last year.

on second thoughts, please don’t. I’d prefer you got on with running a city..

R

[contacts deleted]

—— End of Forwarded Message

Received from Lee Vandervis
Wed, 16 Sep 2015 at 9:27 p.m.

█ Message: And this…

—— Forwarded Message
From: Lee Vandervis
Date: Tue, 15 Sep 2015 21:50:07 +1200
To: David Benson-Pope, Richard Thomson, Grace Ockwell, Sue Bidrose, Sandy Graham
Cc: Dave Cull, Kate Wilson, Chris Staynes, Jinty MacTavish, Hilary Calvert, Aaron Hawkins, Mike Lord, Andrew Whiley, John Bezett, Doug Hall, Neville Peat, Andrew Noone
Conversation: OIA Request
Subject: Re: OIA Request

You might well have stopped for a moment David, to consider the cost of not making LGOIMA requests, or of the enormous savings to ratepayers had LGOIMA requests been honestly and promptly complied with as required by the LGOIMA Act.
It has been recently proven that ex CEO Harland misled Councillors making LGOIMA requests to find out what Farry and Co were up to with Stadium planning/funding, by falsely claiming that the Carisbrook Stadium Trust were not subject to LGOIMA information disclosure requirements. Ex-CEO Harland did this despite having two legal opinions, one local and one ex Wellington, saying that the CST were absolutely subject to LGOIMA information requests. Harland’s deceptions have only come to light as a result of many subsequent LGOIMA requests.
Had Harland processed LGOIMA requests as legally required during his tenure it would highly likely have saved ratepayers many millions in a variety of areas, if not hundreds of millions wasted on our Stadium liability.
If all my 2011 LGOIMA requests for Citifleet information, including all credit card information had been made available as requested under LGOIMA, think how many subsequently stolen vehicles would have been saved and perhaps even the life of a bent manager. Put a price on that David and make sure to request the full cost thereof.
The horrendous cost of not having required relevant information on which to make decisions is the reason we have LGOIMA.
In my opinion, not using the LGOIMA process suggests that you are not doing your job as an elected representative.

Regards,
Cr. Lee Vandervis

———————————

On 15/09/15 6:04 pm, “David Benson-Pope” wrote:

While I agree with the sentiment … If he won’t I wil

This is therefore a request for full details of all lgoima requests made to the dcc by any councillor in the current triennium and the full cost thereof
Yours etc
David Benson-Pope
Sent from my Windows Phone

———————————

From: Richard Thomson
Sent: 15/09/2015 5:27 p.m.
To: Grace Ockwell; Sue Bidrose; Sandy Graham
Cc: Dave Cull; Kate Wilson; Chris Staynes; Lee Vandervis; Jinty MacTavish; David Benson-Pope; Hilary Calvert; Aaron Hawkins; Mike Lord; Andrew Whiley; John Bezett; Doug Hall; Neville Peat; Andrew Noone
Subject: OIA Request

Hi,

Could I please file an official information act request asking what the cost to Council has been of answering Cr Vandervis’s official information act requests over the last year.

on second thoughts, please don’t. I’d prefer you got on with running a city.

R

[contacts deleted]

—— End of Forwarded Message

Posted by Elizabeth Kerr

*Image: toonpool.com – Cat Whisperer by Goodwyn (tweaked by whatifdunedin)

25 Comments

Filed under Architecture, Business, Carisbrook, Citifleet, COC (Otago), Concerts, Construction, CST, Cycle network, DCC, DCHL, DCTL, Delta, Democracy, Design, DIA, DVL, DVML, Economics, Enterprise Dunedin, Events, Highlanders, Hot air, Hotel, LGNZ, Name, New Zealand, NZRU, OAG, OCA, Ombudsman, ORFU, Otago Polytechnic, People, Police, Politics, Pools, Project management, Property, SDHB, SFO, Site, Sport, Stadiums, Tourism, Town planning, Transportation, University of Otago, Urban design

DCC AMAZE —oh, more fraud

DCC logo (fraud) 2

DCC CULTURE OF ENTITLEMENT
‘Enormously disappointing’ —And Enormously Expected.
‘ONE MAN’ did it. An outright fairytale.
DOLLY didn’t, either. More to come !!

### ODT Online Mon, 10 Aug 2015
Further cases of fraud at council
By Chris Morris
The Dunedin City Council says the discovery of five more examples of fraud and theft inside the organisation is “enormously” disappointing. […] Details of the smaller incidents emerged last week, in response to Otago Daily Times questions, a year after the discovery of the Citifleet fraud.
Read more

█ ODT blocks public comments to this item.

ODT 10.8.15 [Source: DCC]

ODT 10.8.15 Further cases of fraud at council p1[screenshot]

Related Posts and Comments:
7.8.15 MOU DCC and TCFT New Aquatic Facility #MosgielPool
4.8.15 Hundreds of DCC Staff receive fraud detection/prevention training
28.7.15 DCC tender fraud includes Citifleet —not for discussion
23.7.15 Publicise: laudafinem.com
207.15 Noble property subdivision —DELTA #LGOIMA
13.7.15 Jeff Dickie: Edinburgh tough, Dunedin (DUD)
4.7.15 DCC Citifleet, [a] Deloitte report leaked
25.6.15 DCC Citifleet COVERUP #screwy
17.6.15 Citifleet: ‘Checkpoint’ interviews Dave Cull
4.5.15 Cr Lee Vandervis: Why I continue to vote. #email
1.5.15 Cr Vandervis unlikely to quit several missions #coverup #naturaljustice
24.3.15 Noble property subdivision —DELTA
23.3.15 Noble property subdivision: “Denials suggest that we have not learned.”
17.3.15 DCC —Delta, Jacks Point Luggate II….
3.1.15 DCC: Street talk NEVER HAPPENED
28.4.15 Today at DCC in pictures
24.4.15 DCC re Dr Bidrose’s time as most senior Citifleet Manager
23.4.15 DCC severely FAILS councillor #naturaljustice #contempt
18.3.15 Lee Vandervis releases emails #Citifleet investigation
13.3.15 Cr Vandervis: LGOIMA request – Citifleet … Deloitte Report
24.12.14 Dunedin: Watching the detectives
1.12.14 Stadium Review: LGOIMA request and 2009 Town Hall speeches
18.12.14 DCC: Deloitte report released on Citifleet
21.11.14 Stadium Review: Mayor Cull exposed
19.11.14 Forsyth Barr Stadium Review
1.9.14 DCC Fraud: Further official information in reply to Cr Vandervis
30.8.14 DCC Fraud: Cr Vandervis … urgent need for facts and record to be public
27.8.14 DCC whitewash on serious fraud, steals democracy from citizens
22.8.14 DCC: Deloitte report referred to the police #Citifleet
3.7.14 Stuff: Alleged vehicle fraud at DCC
1.7.14 DCC: Far-reaching fraud investigation Citifleet
28.5.14 DCC: Audit and risk subcommittee
20.3.14 Delta: Report from Office of the Auditor-General
19.3.14 ORFU: Black-tie dinner, theft or fraud?
26.2.14 DCC: New audit and risk subcommittee a little too late !!
14.2.14 DCC: Broadband AND bicycles #fraudband speed
1.12.13 Secret Commissions Act aka ‘Backhanders Law’

█ For more, enter the terms *deloitte*, *citifleet*, *fraud*, *conduct*, *vandervis*, *delta*, *orfu* in the search box at right.

Posted by Elizabeth Kerr

17 Comments

Filed under Business, Carisbrook, Citifleet, Construction, CST, Cycle network, DCC, DCHL, DCTL, Delta, Democracy, DVL, DVML, Economics, Enterprise Dunedin, LGNZ, Media, Name, New Zealand, NZRU, NZTA, OAG, OCA, Ombudsman, ORFU, People, Police, Politics, Pools, Project management, Property, SFO, Site, Sport, Stadiums, Town planning, Transportation, Urban design

DCC tender fraud includes Citifleet —not for discussion

Mayor Cull is papering over cracks.

QUESTION
Where did the Deloitte report on Citifleet disappear to after it was leaked to ODT? Somewhere deep in a mud tank, at South Dunedin?
Deloitte produced three Citifleet reports; at least two of these show people are liable (present tense) for prosecution.

Where has ODT been to not take the cover off said blocked mud tank.

What makes Dunedin Police so reluctant to prosecute.

Cull and Bidrose “say” just one man, Bachop, is guilty of the +$1.5million Citifleet fraud, which included +152 fleet vehicles lost as well as trade in tyres and parts, and vehicle service contracts (tenders, black market, yawn)….

No wonder Deloitte investigator Kyle Cameron is pissed off at DCC.
No prosecutions ~!!

But back to Monday’s thrashing on tender fraud.
Cr Vandervis has already provided enough evidence to DCC officials, in non public, to add to or start investigations. They don’t want to know.
This is local government at Dunedin, refusing transparency and accountability.

Cr Vandervis hit back, telling the meeting he had provided other evidence to Mr Cull in confidence in the past, and could produce it publicly at the meeting, if needed.

### ODT Online Tue, 28 Jul 2015
Vandervis told to produce ‘evidence’
By Chris Morris
Mayor Dave Cull and Cr Lee Vandervis locked horns yesterday after the latter claimed to have “plenty of evidence” of tender fraud involving the council. The comment, as councillors at yesterday’s full council meeting signed off on a new sensitive expenditure policy, prompted a point of order from Cr Jinty MacTavish, who labelled his comment “disrespectful” and challenged him to produce evidence.
Read more

Report – Council – 27/07/2015 (PDF, 164.6 KB)
Sensitive Expenditure Policy and Procedures

The new policy covered everything from travel and accommodation to entertainment and hospitality, but not contracts and tendering, which Cr Vandervis wanted included as well. (ODT)

About cemetery contracts….

5.3.15 ODT: Praise for council from outgoing manager

Posted by Elizabeth Kerr

7 Comments

Filed under Business, Citifleet, Construction, CST, Cycle network, DCC, DCHL, DCTL, Delta, Democracy, Design, DVL, DVML, Economics, Enterprise Dunedin, Events, LGNZ, Media, Name, New Zealand, NZTA, OAG, OCA, Ombudsman, ORFU, People, Police, Politics, Pools, Project management, Property, SFO, Site, Sport, Stadiums, Town planning, Transportation, Urban design

Dunedin to host LGNZ 2016 conference —FFS TIME TO TAKE IT OUT

Dunedin City Council – Media Release
Dunedin to Host 2016 LGNZ Conference

This item was published on 21 Jul 2015

Dunedin is all set to host the Local Government New Zealand (LGNZ) Conference for 2016 as this year’s conference wraps up in Rotorua today. LGNZ announced Dunedin as the host city for next year’s conference this week. The conference will bring up to 600 delegates to the city from 24-26 July 2016. Delegates will include mayors, chairs, chief executives, councillors and senior management from New Zealand’s councils as well as senior government ministers and stakeholders from the private sector, businesses, central government and non-government agencies.

[PROFLIGATE SPENDER ALERT] Mayor of Dunedin, Dave Cull says, “This is great opportunity for us to showcase Dunedin as a conference destination to the rest of the local government family. We don’t often get the chance to welcome people to Dunedin from every part of New Zealand at once. Delegates will get to experience New Zealand’s only UNESCO City of Literature, Gigatown winner and the country’s wildlife capital firsthand. It will also be an opportunity for all kind of councils to look at the challenges they have in common and discuss solutions.”

[DEBT-SPENDING PROPONENT ALERT] LGNZ President, Lawrence Yule says he is delighted the conference is returning to the deep south. “We have had a number of conferences in Dunedin over the past 20 years and the southern hospitality is always great,” he says. “The city has completed a significant upgrade of the hosting facilities at the Dunedin Centre and Town Hall and you put forward a very strong bid.”

The conference bid was made by Dunedin Venues and Enterprise Dunedin at the start of the year. They presented the Dunedin Centre and Town Hall facilities for the event and used Dunedin’s reputation for innovation, creativity and wildlife as a drawcard.

Contact Dave Cull, Mayor of Dunedin on 477 4000. DCC Link

Related Posts and Comments:
21.5.15 DCC and LGNZ, total losers
2.2.15 LGNZ run by Mad Rooster Yule, end of story
14.1.15 DCC Draft Long Term Plan: more inanity from Cull’s crew pending
13.1.15 Government’s council tax freeze
27.11.14 Auditor-general Lyn Provost #Resign
3.11.14 DCC: What happened to $20 million cash on hand? #LGOIMA
10.10.14 Cull consorts with losers at LGNZ
8.10.14 Stadium: Liability Cull warns ratepayers could pay more to DVML
18.9.14 DCC considers sale of “149 properties”
5.8.14 DCC staff-led CBD projects that impact ratepayers….
30.7.14 Dunedin City Council | Consolidated council debt
5.7.14 DCC’s debt level — who do you believe?
26.6.14 LGNZ #blaggardliars
23.6.14 DCC Annual Plan 2014/15 + Rugby and Rates
12.6.14 Fairfax Media [not ODT] initiative on Local Bodies
11.4.14 Councils: Unaccountable, ready to tax? #DCC #ORC
31.3.14 Audit services to (paying) local bodies #FAIL ● AuditNZ….
29.1.14 Mangawhai, Kaipara —we hear ya!
3.12.13 LGNZ: OAG report on Kaipara
7.10.13 DCC councillors, no idea annual cost of owning, operating FB Stadium
29.9.13 Alert: Dunedin voters —Mayors gain more powers
29.6.13 Audit NZ and OAG clean bill of health —Suspicious!
26.9.13 DCC: Council consolidated debt $623 million
21.4.13 Councils “in schtook” —finance & policy analyst Larry Mitchell
29.10.12 DCC consolidated debt substantially more than $616m to June 30, 2012
30.5.12 Larry Mitchell: 2012 Local Govt League Table Summary
4.7.11 Local government finances

█ For more, enter the terms *dcc*, *dchl*, *annual plan*, *long term plan*, *stadium* or *dvml* in the search box at right.

Posted by Elizabeth Kerr

10 Comments

Filed under Business, Carisbrook, Citifleet, Construction, CST, Cycle network, DCC, DCHL, DCTL, Delta, DVL, DVML, Economics, Enterprise Dunedin, Events, Hot air, LGNZ, Name, New Zealand, NZRU, NZTA, OAG, OCA, Offshore drilling, ORFU, People, Politics, Project management, Property, SFO, Site, Sport, Stadiums, Tourism, Town planning, Transportation, Urban design

Jeff Dickie: Edinburgh tough, Dunedin (DUD)

Further to the contents of an email from Jeff Dickie last month, who was writing from a hotel on Orchard Road at the time:

Supplied. ODT 13.7.15 (page 6)

ODT 13.7.15 Letter to editor Dickie p6

****

INVOICE FRAUD AND MORE

TWO corrupt council officials and two businessmen who supplied them with cash and hospitality have been jailed with a warning they face “significant” sentences.

### HeraldScotland.com Wednesday 17 June 2015
Corrupt Edinburgh council officials face lengthy jail term
[…] Former local authority employees Charles Owenson and James Costello were treated to dances and drinks in lap dancing bars as valuable Edinburgh City Council contracts were secured through bribery. Ex-directors of Action Building Contracts Ltd (ABC Ltd) Kevin Balmer and Brendan Cantwell provided the rewards over the allocation of work for public buildings including schools, care homes and cemeteries.
Following their earlier guilty pleas a sheriff told them that he would continue their case until tomorrow for sentencing at Edinburgh Sheriff Court to consider the information he had been given. But Sheriff Michael O’Grady QC told the four men: “Having regard to the gravity of the offences, it is clear to me the sentences will require to be custodial and require to be significant.” He remanded all of them in jail ahead of sentencing.
Owenson and Costello were provided with hospitality, including corporate seats at Hibs and Hearts football grounds and meals out as well as cash, by Edinburgh-based construction firm ABC Ltd (Action Building Contracts). The contractors even submitted inflated invoices to the local authority for work carried out to cover the costs of the bribes they were paying council officials. Fiscal Keith O’Mahony earlier told the court: “In essence, the council was being charged for the cost of bribing its own officials.”
[…] Police began carrying out enquiries in 2010 as a result of complaints about the statutory notices system and were later informed that senior management had received “a whistleblower letter” alleging that Owenson was showing favouritism when allocating work to contractors. The Crown has raised proceedings to recover crime profits in the case.
Read more

█ 18.6.15 BBC News: Four jailed over Edinburgh City Council bribes

Shades of the ‘Screaming Orgasm cocktails’ saga following Dunedin City Council’s decision to build the stadium. That evening, the board members of Carisbrook Stadium Charitable Trust went out to celebrate, booking their drinks at Alibi Bar & Restaurant to the Ratepayers.
Of course, there have been masses of local big-ticket ‘corruptions’: the stadium land purchases (including for realignment of SH88); the Carisbrook ‘deal’ with Otago Rugby Football Union, and further ‘Otago Rugby’ deals with Dunedin Venues (DVML); the Delta subdivisions and service contracts (Jacks Point and Luggate, and more recently Noble Village); the unravelling Citifleet fraud and insurance scam (substantially greater than 152 fleet vehicles lost off the inventory, allied to ‘traffic’ in car parts, tyres, service contracts, and fluid cash); the Dunedin Town Hall Redevelopment Project (via City Property) yet to be fully detailed; and field lights for Otago Cricket Association…….. et al.

Posted by Elizabeth Kerr

10 Comments

Filed under Architecture, Business, Carisbrook, Citifleet, Construction, CST, DCC, DCHL, DCTL, Delta, Democracy, Design, DVL, DVML, Economics, Events, Media, Name, New Zealand, NZRU, OAG, OCA, Ombudsman, ORFU, People, Police, Politics, Project management, Property, SFO, Site, Sport, Stadiums

Cull’s council spent the cash

The cash was instead used to pay for capital projects, avoiding the expected need to borrow for the work, which reduced the council’s need to borrow by $20 million. –Grant McKenzie

The council had also agreed to another $20 million in carry-forwards for debt-funded project budgets, which shifted allocated funding for delayed projects from one year’s budget to the next. –Grant McKenzie

### ODT Online Mon, 15 Sep 2014
Cull warns debt still hurdle for council
By Chris Morris
The Dunedin City Council cannot afford to get “complacent” despite a significant improvement to its core debt position, Mayor Dave Cull says. Council figures released last week showed its core debt – excluding companies – had dropped by nearly $5.5 million, from $227 million to $221.5 million, in the last financial year. […] the drop was the first time the council’s core debt had decreased since 2002-03, except for when stadium-related debt was transferred from the council to Dunedin Venues Ltd in 2010-11.
Read more

DCC Sep 14, 2014

Dunedin City Council – Finance Committee – September 8 2014
Coverage of the Dunedin City Council Finance Committee held on Monday, 8 September 2014. Minutes, agendas and reports related to this meeting can be found at http://goo.gl/UumsOI

Report – FIN – 08/09/2014 (PDF, 2.3 MB)
Interim Financial Result – 12 Months to 30 June 2014

Report – FIN – 08/09/2014 (PDF, 668.6 KB)
Financial Result – 1 Month to 31 July 2014

Report – FIN – 08/09/2014 (PDF, 391.2 KB)
Waipori Fund Quarterly Report to June 2014

Related Posts and Comments:
11.9.14 DCTL: New treasury manager
● 9.9.14 Mangawhai, Kaipara: Latest news + Winston Peter’s speech [relevance]
1.9.14 DCC Fraud: Further official information in reply to Cr Vandervis
30.8.14 DCC Fraud: Cr Vandervis states urgent need for facts and the record…
26.8.14 DCC: Forensics for kids
23.8.14 DCC public finance forum 12.8.14 (ten slides)
28.4.14 DCC loses City Property manager in restructuring
30.1.14 DCC broke → More PPPs to line private pockets and stuff ratepayers
● 29.1.14 Mangawhai, Kaipara —we hear ya! [relevance]
17.12.13 DCC, Dunedin City Treasury and 3 big banks [Interest Rate Swaps]
10.12.13 DCC putting up cover, walls paper thin [risk exposure VERY HIGH]
14.10.13 DCC: New chief financial officer
4.7.13 Carisbrook: DCC losses

Posted by Elizabeth Kerr

13 Comments

Filed under Business, DCC, DCHL, DCTL, Democracy, Economics, Media, Name, New Zealand, People, Politics, Project management, Property, Sport, Stadiums, What stadium

Town Hall, Dunedin Centre, Municipal Chambers #linked

Dunedin Town Hall (Municipal Chambers) 3Strengthened and up to code, pity about the debt – and DVML

### ODT Online Thu, 7 Mar 2013
RSA choir to ‘open’ town hall on Anzac Day
By Debbie Porteous
After nearly three years and more than $45 million spent on restorations and improvements, Dunedin’s town hall and neighbouring Dunedin Centre are scheduled to reopen next month. And on April 25, a group with long links to the venue, the Dunedin RSA Choir, will be the first to perform there. Choir member David More said they were looking forward to returning to the town hall with their Anzac Day Revue. ”Norma”, the town hall organ, was protected and had fans removed and replaced, but was not otherwise touched during the project, which included work on the town hall, Glenroy auditorium and municipal chambers.

● Contractors would be busy getting the centre ready for handing over to council-owned venue management company Dunedin Venues Ltd by April 5.
● The centre will be officially reopened at a civic reception on April 24.

Read more

Dunedin Town Hall Burton Bros tepapacollections 4Dunedin Town Hall, Burton Bros (Te Papa Collections)

History and significance?
Read the Heritage New Zealand (HNZ) – Registration Reports:
Municipal Chambers – Category 1 (List No. 2197)
Dunedin Town Hall and Concert Chamber – Category 2 (List No. 2150)

Related Posts and Comments:
6.2.12 Ownership and management of the Dunedin Town Hall complex…
2.11.12 Community halls of small-town New Zealand
15.3.11 Cr Dave Cull speech to Town Hall Meeting
21.1.11 DCC opens controversy on Town Hall upgrade, again!
21.7.10 DCC Media Release – Contract let for Town Hall upgrade
2.7.09 Town Hall: Glazed cube and square for Moray Place
1.7.09 Town Hall Dunedin Centre architecture for a What if? second

Dunedin Town Hall (facade to Moray Place) 2

Posted by Elizabeth Kerr

12 Comments

Filed under Architecture, Business, Concerts, Construction, DCC, Design, DVML, Economics, Events, Fun, Heritage, Innovation, Inspiration, Media, Name, NZHPT, People, Politics, Project management, Property, Site, Tourism, Urban design, What stadium