Tag Archives: Contractors

Asbestos contamination at Dunedin Railway Station

[womentravelnz.com]

There’s a new tenancy at the Dunedin Railway Station.

People working on the project had been told the whole underfloor area was safe to enter; that there was plastic down.

Turns out the plastic cover ran short, and a number of site workers had crawled across bare dirt, kicking up a lot of dust as they went – it was found the area had been contaminated with asbestos.

We understand workmen from several companies have been affected.

The Dunedin Railway Station is a council owned property. Affected sitemen have since had their names added to the WorkSafe Asbestos Exposure Database; and Health and Safety meetings have been called to review safety drills and gear provision.

It appears a few people have slipped up along the ‘food chain’ of managerial responsibility for the workers, starting with DCC management (the building owner).

We hear DCC is now paying for workers to be educated on what protection gear they must wear on exposed asbestos worksites.

Related Post and Comments:
19.6.16 Thoughts on ODT Insight : Chris Morris investigates Asbestos plague

Posted by Elizabeth Kerr

This post is offered in the public interest.

9 Comments

Filed under Architecture, Business, Construction, DCC, Democracy, Design, Dunedin, Economics, Education, Events, Health & Safety, Heritage, New Zealand, People, Politics, Project management, Property, Public interest, Site, Tourism, What stadium

Richard Healey on Aurora’s asset value —heralds “massive increase in rates”

Just some little things our beloved leader Mayor Cull isn’t talking about urgently with his Councillors and Dunedin ratepayers at large.

M U S T ● R E A D

Excerpts from Richard Healey’s Facebook 14.2.17:

[click to enlarge]
richard-healey-facebook-14-2-17-comment-excerpts

Related Posts and Comments:
14.2.17 DCC not Delta #EpicFail : Wall Street falsehoods and a world class debt
11.2.17 Shudder : Aurora Energy programme leader likely delusional…
6.2.17 Delta #EpicPowerFail 9 —The Curious Case of Godfrey Brosnan and…
19.1.17 Jarrod Stewart is EXACTLY RIGHT [what would Steve Thompson know]

█ For more, enter the terms *delta*, *aurora*, *grady*, *steve thompson*, *richard healey*, *dchl*, *epicpowerfail* or *epic fraud* in the search box at right.

Posted by Elizabeth Kerr

This post is offered in the public interest.

10 Comments

Filed under Aurora Energy, Business, Central Otago, Construction, DCC, DCHL, DCTL, Delta, Democracy, Design, Dunedin, DVL, DVML, Economics, Education, Electricity, Finance, Geography, Health, Infrastructure, LTP/AP, Name, New Zealand, OAG, Ombudsman, People, Perversion, Pet projects, Politics, Project management, Property, Public interest, Queenstown Lakes, Resource management, SFO, Stadiums, Structural engineering, Technology, Town planning, Travesty, Urban design

—christmas!

Updated post
Tue, 3 Jan 2016 at 2:27 a.m.

Hype O’Thermia
December 25, 2016 at 12:59 pm
Residents delighted with DCC contractors’ quick response to fixogram about pothole. “It used to take forever to get anything done,” said “Jimbo” who asked us not to publish his full name.

Posted by Elizabeth Kerr

christmas-garland-topsailbeach-org

Leave a comment

Filed under Business, DCC, Dunedin, Economics, Infrastructure, Name, Politics, Transportation, What stadium

Thoughts on ODT Insight : Chris Morris investigates Asbestos plague

 

asbestos - dob in a dumper [illawarramercury.com.au]Dob in an asbestos dumper [illawarramercury.com.au]

B E L A T E D L Y
Cowboy New Zealand Governments wake up after YEARS of Devastating Sleep.

New Zealand’s asbestos death toll will climb to about 5100, excluding deaths from asbestosis, which were difficult to determine, a WorkSafe spokesman said. It was expected the peak of asbestos-related disease would not be reached until sometime between 2030 and 2040, the spokesman said. (ODT)

Is the Dunedin City Council opening its eyes quickly enough even with the Amalgamated Workers’ Union (AWUNZ) on its tail ? Good council workmen dead and memorialised in photographs, frightening….

“They worked regularly with the city’s asbestos water pipes – cutting and grinding, kicking up asbestos dust and sweeping up the mess later.” (ODT)

Asbestos cement pipe [cep.bessens.free.fr]Asbestos Magnesia Pipe Insulation [Asbestorama via Flickr.com]Weathered asbestos cement pipe [cep.bessens.free.fr] and asbestos insulation wrap [Asbestorama via flickr.com]

HOW MANY Dunedin City Council (DCC) staff, work crews, contractors and subcontractors have been required to work with asbestos product and exposure to fibres over the years —without comprehensive safety training and correctly specified respirators and safety clothing for individual protection ?
The answer is likely to be unlimited numbers.
Has anything changed at DCC ?
Have all asbestos contaminated DCC-owned sites and work areas been identified to date ?
Are formal protocols and a register in place for personnel who believe they may have been exposed to asbestos and require admittance to a testing regime ?

Asbestos WarningProper warning [shutterstock.com]

ODT Insight: Asbestos: The Silent Killer

### ODT Online Sat, 18 Jun 2016
Asbestos toll will grow
By Chris Morris
The death toll from asbestos-related disease in New Zealand will continue to climb for decades to come, despite a ban on imports of building materials containing the toxic mineral. Environment Minister Nick Smith on Wednesday announced New Zealand would join more than 50 other countries in banning the importation of asbestos-containing materials (ACMs), beginning on October 1, unless exemptions were granted. The move was designed to further reduce the “appalling” death toll caused by asbestos, used in building products for more half a century. It now claimed an estimated 170 lives a year, he said.
Read more

[DCC tragedy] ODT: Suspicions of cancer cluster
Former Dunedin City Council water maintenance staff based at the Midlands St yard say the risks of asbestos were not understood and early precautions inadequate […] a solemn memorial to 14 men taken too soon – photographs of the dead, showing men lost to lung, bowel or prostate cancer, pinned to a noticeboard in the Dunedin City Council’s former Midland St workers’ yard.

ODT: Asbestos: ‘We were totally ignorant’ of risk’ (+ video)
ODT: Asbestos claimed him (+ video)

Other stories:

11.5.16 ODT: Asbestos likely to be cost in future
Asbestos may impact the financial health of the Dunedin City Council’s coffers in years to come but the extent of the cost remains unknown, councillors heard at yesterday’s annual plan deliberations. Group chief financial officer Grant McKenzie told councillors work was under way at present to establish the extent of asbestos use and issues in council-owned assets, but the cost to rectify it would not be known until the investigation was complete.

4.5.16 ODT: Removing asbestos pipes
The Dunedin City Council says it will remove decaying asbestos pipes from public land after their existence at Sullivans Dam was noted by the Amalgamated Workers Union. The pipes are beside sheds near the entrance to the popular fishing spot in Leith Valley Rd. The council yesterday said it had not known the pipes were there.

21.4.16 ODT: Asbestos at pool no threat to public
The Dunedin City Council says there is no immediate threat to the public following the discovery of asbestos at Moana Pool. During a maintenance check of the building early last week, asbestos was discovered in the pump storage area under the pool level of the building and in restricted storage areas away from the pool.

20.4.16 ODT: No ‘immediate health risk’ from Moana Pool asbestos
Group Manager Parks and Recreation Richard Saunders said the maintenance checks identified further inspection and testing for asbestos was needed at several sites, of which Moana Pool was one. […] Initial inspections have been carried out at two other buildings – the Sims building in Port Chalmers, which is leased to a club, and a storage shed located next to Tahuna Park used by Parks and Recreation staff and contractors.

16.4.16 ODT: Council denies asbestos danger
A union says the public could easily have been exposed to cut and broken asbestos pipes left unsecured in a sometimes unattended Mosgiel yard. The Amalgamated Workers Union (AWU) said the pipes at the Dunedin City Council’s Mosgiel wastewater treatment plant were not in a safe state and could have been accessed by children in the residential street.

Asbestos Cement Pipe - close-up of Crocidolite & Chrysotile [Asbestorama via Flickr.com]Asbestos cement pipe, close-up of Crocidolite and Chrysotile
[Asbestorama via flickr.com]

ASBESTOS (pronounced /æsˈbɛstəs/, /æzˈbɛstəs/ or /æzˈbɛstɒs/) is a set of six naturally occurring silicate minerals, which all have in common their eponymous asbestiform habit: long (roughly 1:20 aspect ratio), thin fibrous crystals, with each visible fiber composed of millions of microscopic “fibrils” that can be released by abrasion and other processes. They are commonly known by their colors, as blue asbestos, brown asbestos, white asbestos, and green asbestos.

Asbestos mining existed more than 4,000 years ago, but large-scale mining began at the end of the 19th century, when manufacturers and builders began using asbestos for its desirable physical properties: sound absorption, average tensile strength, resistance to fire, heat, electricity, and affordability. It was used in such applications as electrical insulation for hotplate wiring and in building insulation. When asbestos is used for its resistance to fire or heat, the fibres are often mixed with cement or woven into fabric or mats. These desirable properties made asbestos very widely used. Asbestos use continued to grow through most of the 20th century until public knowledge (acting through courts and legislatures) of the health hazards of asbestos dust outlawed asbestos in mainstream construction and fireproofing in most countries.

Prolonged inhalation of asbestos fibres can cause serious and fatal illnesses including lung cancer, mesothelioma, and asbestosis (a type of pneumoconiosis). Illness from asbestos exposure can be found in records dating back to Roman times. Concern in modern times began in the 20th century and escalated during the 1920s and 1930s. By the 1980s and 1990s asbestos trade and use was heavily restricted, phased out, or banned outright in an increasing number of countries.

The severity of asbestos-related diseases, the material’s extremely widespread use in many areas of life, its continuing long-term use after harmful health effects were known or suspected, and the slow emergence of symptoms decades after exposure ceased made asbestos litigation the longest, most expensive mass tort in U.S. history and a much lesser legal issue in most other countries involved. Asbestos-related liability also remains an ongoing concern for many manufacturers, insurers and reinsurers.
Read more at Wikipedia: Asbestos

Myth: Asbestos Fibres are firmly locked in a cement matrix.
Fact: Asbestos Fibres are readily released from deteriorated or weathered surfaces.

Myth: Asbestos-cement cannot be crumbled to powder by hand pressure.
Fact: Products such as asbestos-cement corrugated siding become friable from damage.

Myth: Asbestos-cement products present no exposure hazard to building occupants.
Fact: Asbestos roofing and siding can release fibres inside as well as outside the building. Not all asbestos-cement roofing and siding remain in as good condition. In many countries, the inside of asbestos-cement roofing and siding is subject to the normal activities of the occupants that can release fibres from the surfaces. An asbestos-cement panel can be vibrated by wind, causing some abrasion of the edges.

Myth: Asbestos-cement pipes present no health or environmental hazard.
Fact: Health and environmental hazards start during the manufacturing process when the ends of the pipes are ground and the waste is disposed of carelessly. Fine dust produced during installation of the pipes is a hazard to the workers and community. When the pipes are dug up and removed, fibres are released as they are broken and crushed. Pressure pipe for water distribution was made with crocidolite and amosite as well as chrysotile.

Myth: Paint and encapsulants offer permanent protection against asbestos fibre release.
Fact: Paint and encapsulants deteriorate and take asbestos fibres with them when they peel off. Why is it necessary to protect a material that is touted for its weather-resistance and durability, yet encapsulants for asbestos-cement roofing and siding are widely marketed. Encapsulants are a form of paint, and a good paint job begins with surface preparation. The hope is that no one sands asbestos-cement roofing and siding before they paint or encapsulate it, because of the obvious dust and health hazard created.

█ NEW ZEALAND LEGISLATION

The Health and Safety at Work (Asbestos) Regulations 2016 came into force on 4 April 2016. They set out the new rules around the removal of asbestos, and the circumstances where WorkSafe must be notified.

New licensing system for asbestos removal
A national licensing system for asbestos removal was introduced on 4 April 2016. The licences available under the new asbestos regulations are:

Type of licence : What asbestos can be removed?

Class A
Any type or quantity of asbestos or asbestos containing material, including:
• any amount of friable asbestos or asbestos containing material (ACM)
• any amount of asbestos contaminated dust or debris (ACD)
• any amount of non-friable asbestos or ACM.

Class B
Any amount of non-friable asbestos or ACM
ACD associated with removing any amount of non-friable asbestos or ACM.

No licence is required for removing:
• up to 10 m2 of non-friable asbestos or asbestos-containing material over the whole course of the removal project for the site
• asbestos-contaminated dust that is associated with this volume of asbestos or asbestos-containing material, and/or any associated minor volume of asbestos-contaminated dust or debris.

A new role of asbestos assessor has been developed. A licensed asbestos assessor will provide air quality monitoring during removal work, inspect the finished job and provide a clearance certificate. A licensed asbestos assessor will be required to assess Class A asbestos removal work from 2018 onwards.

Current Certificate of Competence holders will be able to continue removing asbestos (in the categories specified on their certificate), and supervise asbestos removal, until their certificate expires.

Related Posts and Comments:
11.5.16 DCC DRAFT Annual Plan 2016/17 —Harden up, Council [survey budget]
10.4.16 DCC: Council meeting Mon 11 April at 1pm [DCC sites – see Comments]
25.11.15 Mayor Cull and the GREAT Asbestos Defeat ….trucks in toxic waste
27.1.10 Stadium: CST to clean up contaminated land
14.10.09 Questions about landfill charges + DCC reveals contaminated sites

Posted by Elizabeth Kerr

Election Year. This post is offered in the public interest.

KONICA MINOLTA DIGITAL CAMERAAsbestos-cement roofing before and after cleaning [specialistroofcleaning.com]

Asbestos-cement roof shingles [Asbestorama at flickr.com]Asbestorama: Asbestos-cement roof shingles [flickr.com]

10 Comments

Filed under Architecture, Business, Construction, DCC, Democracy, Design, Dunedin, Economics, Education, Finance, Heritage, Housing, Infrastructure, Media, Name, New Zealand, Ombudsman, People, Politics, Pools, Project management, Property, Public interest, Resource management, Site, Stadiums, Town planning, Travesty

DCC: Slip in service levels, why?!

ODT 30.5.14 (page 12) [click to enlarge]
ODT 30.5.14 Letters to editor Barnes, Cook, Morrison (page 12) 1

### ODT Online Mon, 19 May 2014
Councillor urges better standard of work
By Debbie Porteous
Parts of Dunedin are lacking basic maintenance and city council staff need to put pressure on contractors to improve their performance, a Dunedin city councillor says. Cr Andrew Noone, from the Waikouaiti-Chalmers ward, said the untidy state of roadside berms, gutters, ditches and creeks and an apparent slip in service levels were the main issues he heard about from constituents.
Read more

Posted by Elizabeth Kerr

Leave a comment

Filed under Business, DCC, Hot air, Media, Name, People, Politics, Project management, Stadiums, What stadium

DCC: Mr Avery, your choice —infrastructure maintenance or flood damage?

The council would investigate problems at the corner of St Andrew and George Sts.

### ODT Online Tue, 17 Dec 2013
Storm floods city shops
Parts of Dunedin were flooded late yesterday afternoon when a thunderstorm struck, causing havoc for some central-city businesses. In less than 30 minutes, 15mm of rain fell in the central city, with 18.8mm falling between 4pm and 5pm. Water washed into about 20 businesses, mostly in George St between the Wall Street mall and the St Andrew St intersection.
Read more + Images

RAIN [tvnz.co.nz] screenshot 3

An LGOIMA request to uncover and unblock the city council’s infrastructure services (actual) activity log of street maintenance works as well as the record of council consultation with affected building owners (including City Property for Wall Street Mall which cops it every time there’s a slight deluge…), and all associated complaints received by the council would be useful in “forward planning”.

As for temporary road closures in the CBD during heavy rain and flooding, what is the history? Have there been attempts to do this in the past? During yesterday’s rain there was certainly enough time to effect temporary stopping to help minimise damage to property caused by vehicle movement.

****

### dunedintv.co.nz July 15, 2013 – 8:02pm
Council will consider the cost of rain damage to the city
The Dunedin City Council will tomorrow consider the cost of damage to the city from storms and rain.
Video

What came of this consideration? Apparently, nothing for the CBD.

****

Dunedin City Council – Media Release 17 June 2013
Heavy Rain Causes Flooding, Slips
Contractors are busy clearing slips and fallen trees from Dunedin roads after heavy rain causes problems across the wider city. Cont/

****

DCC Three Waters Strategy…
Management of Water Wastewater and Stormwater (The 3 Waters)
Our main objective is to protect public health and safety by delivering enough safe drinking water to, and safely removing waste and storm water from, everyone connected to the network, with minimal impact on the environment and at an acceptable financial cost. We also aim to provide protection from flooding and erosion as well as controlling and reducing pollution in stormwater discharges to waterways and the sea. As well as delivering services today, we need to plan for the future, making sure we will be able to deliver the service that future generations will need. Cont/

****

Dunedin City Council – Media Release 06 Dec 2013
City Care Confirmed as Contractor
City Care has been awarded the tender to maintain Dunedin’s water and wastewater network. The contract, which starts on 28 February 2014, is expected to deliver annual savings of at least $350,000. The annual contract value is $4.6 million a year, with an additional $159,000 of transition costs in the first year. City Care employees will carry out the maintenance work on the water and wastewater network, such as turning up to fix a burst water main or a blocked sewer. Cont/

Posted by Elizabeth Kerr

15 Comments

Filed under Business, Construction, DCC, Design, Economics, Media, Name, People, Politics, Project management, Property, Site, Tourism, Town planning, Urban design

DVML issues and rankles [Burden’s reply]

Received.
Tuesday, December 03, 2013 8:59 AM

Cr Lee Vandervis forwards copy of email correspondence, noting: “An unsatisfactory set of responses to my questions of Darren Burden, now departed, follows.”

—— Forwarded Message
From: Darren Burden [DVML]
Date: Wed, 30 Oct 2013 04:14:39 +0000
To: Lee Vandervis
Cc: Paul Orders [DCC], Sue Bidrose [DCC], Sandy Graham [DCC]
Conversation: DVML urgent issues to be resolved
Subject: FW: DVML urgent issues to be resolved

Lee

Paul forwarded to me your recent comments about Dunedin Venues which I briefly discussed with him. He has asked that I respond to you on the points raised:

A. We have recently installed toilet facilities to Level 2A which in an ideal world would have been installed as part of the original build. However the original build did include the infrastructure for this such as capped services. The work carried out has been consented by the building control department. The cost of the work is within the authority of the DVML board and does not need council approval. In respect of comments from Mr Anderson I have never been introduced to him and was not informed by DVAV that anyone by this name has worked at the stadium for the last 2 years. Refer to point C about DVAV.

B. We have 8 sets of grow lights which cost approximately $35,000 to build. These were manufactured through local suppliers and contractors. These are not used to grow an “ailing” pitch rather to assist worn patches in their re-growth particularly during the winter months. This is not unusual for most stadiums and in fact the size (and cost) of ours are considerably smaller than elsewhere. We estimate the running cost for these in any given year is in the order of $8,000. As a side note, if the pitch had the same amount of use as Carisbrook used to we probably would not need them. However they are of assistance in respect of the significant use the stadium is getting (last financial year we had 60 main bowl events which compares, we believe, with 21 at Eden Park, 14 at Waikato, and 47 at Westpac). Again, our board had authority to approve this cost so did not need council approval. In respect of the electricity cost it should be noted that the stadium has four substations which provides for surety of supply, however this means that our fixed charges are proportionally high to the overall bill. Power usage would be about 50% of our electricity bill.

C. Dunedin Venues has a very good record at paying contractors on time – our monthly financial reports substantiate this. We do, however, have a current dispute with DVAV which is being dealt with through the provisions of the contract by both parties agreeing to go to arbitration. We are not a party to any contractual arrangement between DVAV and Mr Anderson, so any issues that he has would be for him to address directly with DVAV.

Kind regards

DARREN BURDEN
CHIEF EXECUTIVE OFFICER
_____________________________________________

DDI 03 479 4530 M 029 200 1579
E darren.burden@dunedinvenues.co.nz
W http://www.dunedinvenues.co.nz

From: Paul Orders [DCC]
Sent: Friday, 11 October 2013 3:56 p.m.
To: Darren Burden [DVML]
Subject: FW: DVML urgent issues to be resolved
Importance: High

Darren,

Any chance you could draft a response to Lee on each of the points he’s making here.

It would be probably be helpful if we could talk through the response before it goes to Lee.

Regards,

Paul

From: Lee Vandervis
Sent: Thursday, 10 October 2013 12:42 p.m.
To: Paul Orders [DCC]
Cc: Sue Bidrose [DCC]; Sandy Graham [DCC]
Subject: DVML urgent issues to be resolved
Importance: High

Hi Paul,

The last month has been chock full of people complaining to me about the on-going goings-on at DVML.
I again strongly urge you disestablish this dysfunctional DVML board of directors and review management options.

A – I have it on first hand authority that enormous sums are currently being spent on new toilet blocks and facilities that perhaps should have been part of the original build.
Much work has been completed on level 2 amongst other construction. None of this work has been authorised by Council as far as I am aware, and I have been taking keen interest.
I am also advised that substandard work guaranteeing long term high maintenance [like the substitution of non-tanalised timber where tanalised was specified that I previously advised you of and showed photographic evidence]. Martin Andersen [see email below] has worked at the Stadium for 2 years and can give details.

B – Specifically not authorised by Council was the funding for expensive grow-lights for the ailing turf, which Councillors rejected over a year ago as NOT TO BE FUNDED, as DVML, Farry and Co had assured us that the turf would grow satisfactorily under the EFTE roof. Extensive banks of grow-lights have been used regularly for many months now despite the Council decision, causing further direct lights cost and injurious augmentation of an already obscene electricity cost [$250,000 per year without grow lights – when the whole city’s electric lighting costs $1.5 million].

C – DVML have been refusing to pay a number of contractors in a timely fashion, specifically DVAV [confirm with contacts below] for extensive AV work since March of this year, and are now being expensively sued for breach of contract.

Council has recently bailed out DVML for its spending of unauthorised millions [I have consistently recorded my vote against] and the obvious reasons for not bailing them keep appearing as above.
This has happened on your watch Paul, and I have been forthright in warning you about it.

I demand that action be immediately taken to investigate all DVML decisions, past and present and that a full report on past failings and options be brought to Council asap. The $20 million annual running cost bleeding of the ratepayer by the Stadium must end now.

Regards,
Cr. Lee Vandervis

—— Forwarded Message
From: Megan Anderson
Date: Wed, 9 Oct 2013 00:01:18 +0000
To: Lee Vandervis
Subject: Non payment

Good Afternoon Lee,

As per our conversation this is to confirm that I worked for DVAV and we are still awaiting payment as DVAV are still awaiting outstanding invoice payments from DVML, for confirmation of this please don’t hesitate to contact Mike Cook on [mobile number deleted. -Eds].

Thanks

Marty and Megan Anderson

Sent from Windows Mail

—— End of Forwarded Message

Editor’s Note:
Mike Cook is the sole director of DV Audio Visual Limited. DVAV was incorporated on 13 July 2012. In Forsyth Barr Stadium marketing literature, Dunedin Venues say they “work closely with DVAV who are a full service audio visual company delivering audio visual, lighting, event production, conference and technical support services”.

Related Post and Comments:
30.11.13 DVML in disarray

Posted by Elizabeth Kerr

12 Comments

Filed under Business, DCC, DVL, DVML, Economics, Hot air, Name, New Zealand, People, Politics, Project management, Property, Site, Sport, Stadiums

Stadium caterers’ no show

The corporate suites had to wait for service and there were lengthy queues at some food and beverage outlets.

### ODT Online Tue, 6 Mar 2012
Catering staff no-shows annoy stadium boss
By Steve Hepburn
More than a third of the catering staff did not turn up for Saturday night’s Highlanders game, leaving Forsyth Barr Stadium boss David Davies disappointed. The Highlanders beat the Crusaders 27-24 at the stadium, the first time it hosted a Super 15 match, but Davies, the chief executive of Dunedin Venues Management Ltd, said he was not happy with the way the stadium had performed.
Read more

****

A little too late from the clock man…

### ODT Online Tue, 6 Mar 2012
Opinion
Pursuing stadium’s promise means hard work
By Ian Taylor
Oh, what a night! If anyone needed evidence of the importance that rugby and the stadium have to the future of this city then you need look no further than Saturday night and the wonderful occasion that was The Highlanders v The Crusaders.

We also deserve better than being treated as a captive audience who will pay whatever prices are set for a beer, a pie, a sandwich. The experience needs to extend beyond the rugby field. Families need to be able to enjoy a night at the stadium as a great night out. Send them home feeling ripped off and you have lost them forever. Customer service 101.

Read more

Posted by Elizabeth Kerr

7 Comments

Filed under Architecture, Business, Design, DVML, Economics, Events, Name, People, Politics, Project management, Sport, Stadiums

Is there a conflict of interest?

### ODT Online Wed, 21 Sep 2011
Conflict of interest claim denied
By David Loughrey
Anti-stadium campaigner Bev Butler has again taken aim at the people who worked to build the Forsyth Barr Stadium, but this time she has got no backing from a former ally, now mayor, Dave Cull. Ms Butler’s latest target is Dunedin City Holdings Ltd (DCHL) director Mike Coburn, who has also worked on the project delivery team that made sure the stadium was built. She claimed there was a conflict of interest in the role, and that two invoices she unearthed to Mr Coburn’s company Ruboc Holdings for “casual corporate suite rental” last year for the All Blacks v Wales game, showed about $6000 that should not have been paid for by ratepayers.
Read more

****

This morning, Bev Butler emailed the following notes and information to What if? Dunedin…

She says:
• Attached are 23 Ruboc Holdings invoices.
• Below is the covering note with [Mike] Coburn’s explanation.
• My overall comment: “The public will be shocked at the pure unadulterated greed.”
• My comment on the covering note by Coburn is “Pathetic”.

Notes:
DCHL director Mike Coburn’s company, Ruboc Holdings Ltd, invoiced the Carisbrook Stadium Trust (CST), then paid for by DCC, for casual lease of a corporate box for the All Blacks vs Wales test game last year.

The invoice was for $4,429.69 (incl GST). This was approved by Malcolm Farry, CST chairman. Note also the invoice is dated 12 May 2010 and payment made a month in advance of the rugby All Blacks test.

Another invoice was for Additional Test tickets $2,409.69. From the invoices this was a day out for the Project Delivery Team and ……..

Total of all Ruboc invoices: $83,370.04 (incl GST)

Coburn started claiming fees from 9 March 2009. This is before the Hawkins contract was signed on 27 April 2009. He was right in there from the start.

Some invoices claim expenses for meals, taxis, phone, parking and accommodation. Not sure where the accommodation would fit in as Coburn lives in Dunedin and there are no claims for travel elsewhere.

Mike Coburn is the sole director and sole shareholder of Ruboc Holdings Ltd. He is the company.

Mike Coburn was being paid $1000 per day as Project Delivery Team member to push the stadium construction further while failing in his duty as a director of DCHL to inform DCC that DCHL was unable to supply dividends to pay off the stadium debt.

Mike Coburn invoiced the CST $4,429.69 for the one day casual hire of his corporate box so that the Project Delivery Team could watch the All Blacks vs Wales test match.

This invoice was approved by Malcolm Farry then sent to DCC for payment under the guise of construction cost.

Mike Coburn also invoiced CST $2,409.69 for extra Test tickets for the same All Blacks vs Wales game.

[Malcolm] Farry then claimed this as a construction cost of the stadium.

Did Coburn also claim $1000 payment for attending the test match day as well because he was ‘working’?

Who were the other tickets bought for?
Who are the members of the Project Delivery Team?
Are these members all being paid $1000 per day and did they all get paid $1000 to attend the rugby as well as their tickets paid for?
Do any of these other members also have conflicts of interest?

Covering note from DCC:
Dear Bev
As previously indicated, here is the covering note for the release of Ruboc invoice information.

“Please find attached the information requested regarding Ruboc Holdings Ltd invoices. All the invoices held by the Council have been released. The invoices, in the main, cover Ruboc Holding’s[sic] time in respect of the many meetings attended relevant to the delivery of the stadium project including those with the PDT, DCC committees, Council meetings, University, DVML and Hawkins.

“Two invoices relate to the rental of a suite at Carisbrook. The hosting of contractors at Carisbrook was an exercise by the PDT to strengthen the working relationship primarily between the main contractor Hawkins, subcontractors and Arrow International Ltd at a time when they were facing significant challenges to reduce costs to remain within budget. Initially there was only sufficient interest to fill part part the suite and Ruboc committed to the balance but as word got around, enthusiasm grew as did the numbers, and Ruboc had to forgo the balance, hence two invoices.

“I trust this answers your enquiry.”

Sandy [Graham]
[DCC governance manager]

The invoices:
Ruboc Holdings – 00000041 – $900
Ruboc Holdings – 00000047 – $2,025
Ruboc Holdings – 00000053 – $900
Ruboc Holdings – 00000065 – $1,800

Ruboc Holdings – 00000069 – $1,487.50
Ruboc Holdings – 00000075- $5,580
Ruboc Holdings – 00000112 – $2,180.50
Ruboc Holdings – 00000125 – $2,197.50

Ruboc Holdings – 00000130- $2,120
Ruboc Holdings – 00000133 – $3,937.50
Ruboc Holdings – 00000138 – $3,583.50
Ruboc Holdings – 00000148 – $2,141.95

Ruboc Holdings – 00000150 – $4,459.25
Ruboc Holdings – 00000167 – $3,240
Ruboc Holdings – 00000180 – $3,330
Ruboc Holdings – 00000190 – $4,680

Ruboc Holdings – 00000198 – $4,950
Ruboc Holdings – 00000213 – $4,275
Ruboc Holdings – 00000221 – $2,475
Ruboc Holdings – 00000234 – $4,725

Ruboc Holdings – 00000246 – $5,625
Ruboc Holdings – 00000253 – $2,700
Ruboc Holdings – 00000261 – $4,050

Posted by Elizabeth Kerr

15 Comments

Filed under Construction, CST, DCC, DCHL, Economics, People, Politics, Project management, Site, Sport, Stadiums

Dunedin City Council contracts

### ODT Online Mon, 30 May 2011
DCC contractors in firing line
By Chris Morris
The performance of Dunedin City Council contractors holding $10 million maintenance contracts is to be scrutinised, amid claims the workers are literally spraying money away. Council staff, together with Crs Andrew Noone and Lee Vandervis, will meet Fulton Hogan representatives next month to discuss complaints about shoddy and inefficient work practices.
Read more

Posted by Elizabeth Kerr

4 Comments

Filed under Economics, Geography, Politics, Project management

ODT: “Stadium site: 2 accidents, 11 ‘near misses'”

### ODT Online Tue, 16 Mar 2010
Caution urged for stadium tours
By Chris Morris
A more cautious approach to visitors may be needed at Dunedin’s Forsyth Barr Stadium, contractors are warning, following two accidents and 11 “near misses” at the construction site. A breakdown of health and safety incidents at the site showed there had been 27 incidents in the 228,000 man-hours since construction of the roofed stadium began last year, a report by project manager Arrow International said.

The report suggested “prudence” when considering future requests for site visits, following a “marked increase” in the number of tours.

Read more

Post by Elizabeth Kerr

26 Comments

Filed under Construction, Project management, Site, Stadiums