Daily Archives: February 24, 2017

Delta implicated in significant Saddle Hill fire (October 2015)

Channel 39 News:

Deputy editor Craig Page says tomorrow’s ODT carries “a really strong story”.

“We talked earlier about Delta being the story that keeps giving, and that’s the case”.

“We’ve got a group of seven Saddle Hill property owners who, we understand, are suing Delta for more than two million dollars, because they believe they [Delta] were to blame for the fire back in 2015, quite a significant fire around Saddle Hill area, [with] something like ten buildings including garages damaged.

“They’re not saying too much about their claims but we understand it’s to do with mismanagement of some safety equipment in the power line there, branches fell on the lines which started the fire and some sort of switch shouldn’t have turned back on, but did…..”

News presenter Craig Storey: “We’ll see you in court.”

Craig Page: “Exactly.”

****

saddle-hill-fire-7-oct-2015-jsnnz-at-imgur-comSaddle Hill fire 7 Oct 2015 [JSNNZ at imgur.com]

TheManCave Published on Oct 6, 2015
Large fire on Saddle Hill Dunedin 2015
A large fire close to Dunedin city on Saddle Hill with multiple fire engines and helicopters with monsoon bucket, with very high winds fanning it and making it hard to get under control.

****

### ODT Online Wed, 14 Oct 2015
Saddle Hill fire warning to Taieri residents
By Timothy Brown
….The warning of a hot, dry El Nino summer and last week’s Saddle Hill blaze should remind all residents to prepare for the worst and be vigilant, Otago Rural Fire Authority deputy principal rural fire officer Graeme Still says. Nine structures – including two homes – were damaged by the blaze which swept through between 50ha and 100ha of land and put one woman in Dunedin Hospital with serious throat burns. “People need to just be aware,” Mr Still said. “Keep a bit of defensible space around their structures, especially living in the rural areas. Keep their lawns mowed and spouting clear of debris.” Those carrying out permitted burns needed to watch the fire danger and ensure their fires were out. […] The Saddle Hill fire now appeared to be under control, but firefighters would maintain a watch on it until the area received heavy rain.
Read more + Images

### ODT Online Thu, 28 July 2016
Saddle Hill fire ‘chaotic’ – review
By Shawn McAvinue
An operational review of the “erratic” Saddle Hill fire in Dunedin last year has revealed the first ground crews at the scene had to battle the blaze for more than two hours with “chaotic” communication, including cluttered radio channels, forcing many key decisions to be made by cellphone. A key finding of the review – undertaken by the Otago Rural Fire Authority (ORFA) and New Zealand Fire Service – was the communication between fire crews on the ground was compromised during the first hours of the fire. The crews were called to a fire in Morris Rd at 1.51pm on October 7 last year.
Read more

Posted by Elizabeth Kerr

This post is offered in the public interest.

8 Comments

Filed under Business, Delta, Democracy, Dunedin, Economics, Electricity, Events, Infrastructure, Media, New Zealand, People, Property, Public interest, Travesty

Aurora Energy at ODT 24.2.17 follows #LGOIMA

Broad spectrum (?!) LGOIMA request from earlier this week and interim acknowledgement:

From: Elizabeth Kerr
Sent: Monday, 20 February 2017 7:24 PM
To: Grady Cameron
Cc: Elizabeth Kerr
Subject: Aurora Energy Ltd – Official Information Request (LGOIMA)

Attention Grady Cameron
Chief Executive, Aurora Energy Ltd

Dear Grady

How is Aurora Energy Ltd funding the $30million pole replacement programme you speak about – from capex (capital expenditure), opex (operational expenditure), a combination of the two? or by other means? (please state)

Will Aurora Energy Ltd attempt to raise line charges for Otago power consumers, to achieve the number of (dangerous) pole replacements required in the next 3-5 years – how soon will line charges increase and by how much given regulatory scrutiny by the Commerce Commission?*

Is Aurora Energy Ltd solvent at this time? Explain.

Please provide any financial detail(s) salient to these matters.

Sincerely

Elizabeth Kerr
Dunedin

*emphasis added 24.2.17

—————————————-

From: Grady Cameron
Sent: Wednesday, 22 February 2017 1:02 p.m.
To: Elizabeth Kerr
Subject: Aurora Energy Ltd – Official Information Request (LGOIMA)

Dear Elizabeth

Thank you for your enquiry. We acknowledge receipt of your official information request received by us on 21 February regarding Aurora Energy (our reference 0945).

We will endeavour to respond to your request as soon as possible and in any event no later than 21 March, being 20 working days after the day your request was received. If we are unable to respond to your request by then, we will notify you of an extension of that timeframe.

Kind regards,
Glenda

****

Received.
Fri, 24 Feb 2017 at 1:58 a.m.

[click to enlarge]

ODT 24.2.17 (page 4)

odt-24-2-17-aurora-planned-power-outages-p4

ODT 24.2.17 (page 5)

odt-24-2-17-aurora-energy-notification-of-electricity-delivery-prices-p5

Posted by Elizabeth Kerr

This post is offered in the public interest.

2 Comments

Filed under Aurora Energy, Business, Central Otago, Construction, DCC, DCHL, DCTL, Delta, Democracy, Design, Dunedin, Economics, Education, Electricity, Finance, Geography, Health, Infrastructure, Media, Name, New Zealand, OAG, Ombudsman, People, Perversion, Pet projects, Politics, Project management, Property, Public interest, Queenstown Lakes, Resource management, SFO, Technology, Tourism, Town planning, Travesty, Urban design, What stadium