On campus, nothing much.
Demolition continues at the old dental school.
Received from Carol Roberts
Tue, 28 Jun 2016 at 11:12 p.m.
Artist’s impression [Image supplied]
Dental School
Project manager Aurecon’s project director resigned 2-3 weeks ago. This will be the 4th or 5th PM for this job. Aurecon won the job because of this person’s credentials…. shades of the prior Opus Dental school debacle.
Research Building
The PM for RCP New Zealand, resigned about 2 months into the project 2 weeks ago…. Construction of the ‘Animal Research Support Facility’ for the south campus was scheduled to start in August and be completed in February 2018.
Science Building
Leighs onsite QS/PM has left, the Leighs project director, who is supposed to be onsite 3-4 days a week, goes weeks without a visit, and Leighs general manager, Graeme Earl, has left…. Leighs are looking for a replacement.
Leighs AWOL…and behind programme at Science.
A further development
Local Quantity Surveying firms elbowed out of the way
(not implying the university!) Local Institutions are paying substantial premiums (including 6 figures) to out of town firms.
[ends]
—